Lightning Risk Assessment

Jump to section

Overview

The Lightning Risk Assessment calculator evaluates the need for lightning protection systems (LPS) per IEC 62305-2 — Protection against lightning: Risk management. It calculates risk R1 (loss of human life) and determines whether a lightning protection system is required, and if so, at which protection level (LPL I–IV).

The calculator provides:

  • Collection area — equivalent area attracting lightning strikes
  • Expected strikes — annual frequency of dangerous lightning events (Nd)
  • Risk assessment — R1 broken into RA (touch/step), RB (fire/damage), RC (system failure)
  • Protection decision — whether LPS is required
  • Protection level — LPL I, II, III, or IV with rolling sphere radius and mesh size

Input Parameters

Structure

ParameterDefaultRangeDescription
structure_length40 m1 – 1000Structure length
structure_width20 m1 – 1000Structure width
structure_height10 m1 – 300Structure height

Lightning Environment

ParameterDefaultDescription
flash_density2 fl/km²/yrGround flash density Ng (from local lightning data)
location_factorflatRelative location, Cd per IEC 62305-2 Table A.1: surrounded by taller objects (0.25), flat = surrounded by objects of the same height or smaller (0.5), moderate = isolated, no objects in the vicinity (1.0), exposed = isolated on a hilltop or knoll (2.0)

Structure Properties

ParameterDefaultDescription
structure_typenon_metal_roofRoof and structure material → PB probability
occupancyoccupiedOccupancy level → LA loss factor
fire_riskordinaryFire/explosion risk → LB loss factor

Systems & Protection

ParameterDefaultDescription
internal_systemslow_voltageService lines connected to the internal systems (none, LV power, telecom, LV power + telecom) → number of lines n in PC
consequence_of_failurestandardConsequence of system failure → LC factor
touch_step_protectionnoneTouch/step voltage measures → PA factor
surge_protectionnoneCoordinated SPD system on every connected line → PSPD (IEC 62305-2 Table B.3)
existing_lpsnoneExisting LPS level → reduces PB by efficiency

Output Results

OutputSymbolUnitDescription
Collection AreaAdm²Equivalent area attracting direct strikes
Expected StrikesNd/yrAnnual expected dangerous lightning events
Risk RARA—Injury from touch/step voltages
Risk RBRB—Physical damage (fire, explosion)
Risk RCRC—Failure of internal systems
Total RiskR1—RA + RB + RC
Tolerable RiskRT—10-5 for loss of human life
Protection Required—Yes / NoWhether R1 > RT
Protection LevelLPLI – IVRequired lightning protection level
Rolling Sphere—mRolling sphere radius for LPL (20 / 30 / 45 / 60 m)
Mesh Size—mMaximum mesh size (5 / 10 / 15 / 20 m)

Formulas

Collection Area (IEC 62305-2 eq. A.2)

Ad = L×W + 2×(3H)×(L+W) + π×(3H)²

The 3H factor accounts for the attractive radius of the structure. For a 40×20×10 m building: Ad = 800 + 3,600 + 2,827 ≈ 7,227 m².

Expected Dangerous Events (IEC 62305-2 Annex A)

Nd = Ng × Ad × Cd × 10-6

Risk R1 Components

RA = Nd × PA × LA
RB = Nd × PB × LB
RC = Nd × PC × LC,  PC = 1 − (1 − PSPD × CLD)n
R1 = RA + RB + RC

The probabilities and losses are category values chosen by the inputs (a simplification of the IEC 62305-2 Annex B/C factor products). An existing LPS multiplies PB by (1 − efficiency).

PC follows IEC 62305-2 B.4: each connected service line contributes PC,i = PSPD × CLD, and the lines combine as PC = 1 − (1 − PC,1)(1 − PC,2)…, so connecting more lines raises PC. The calculator simplifies this to one category: every connected line is taken as an unshielded aerial or buried line (CLD = 1, Table B.4) and the selected SPD level is applied to all of them. With no connected line (stand-alone systems) CLD = 0 and PC = 0. Shielded or bonded lines, isolating interfaces and SPDs better than LPL I (PSPD 0.005–0.001) are not modelled.

FactorInputValues
Cdlocation_factorsurrounded by higher objects 0.25, flat (same height or smaller) 0.5, moderate (isolated) 1, exposed (isolated on a hilltop) 2 — Table A.1
PAtouch_step_protectionnone 1, warning notices 0.1, electrical insulation 0.01, equipotential bonding 0.01
PBstructure_typemetal roof + metal structure 0.001, non-metal roof + metal structure 0.01, non-metal roof 0.1, thatched roof 0.3
PB multiplierexisting_lpsnone 1, IV 0.2, III 0.1, II 0.05, I 0.02
n (lines)internal_systemsnone 0 (PC = 0), low voltage 1, telecom 1, LV and telecom 2
CLD—1 (unshielded line, Table B.4)
PSPDsurge_protectionnone 1, spd_1 (LPL III–IV) 0.05, spd_2 (LPL II) 0.02, spd_3 (LPL I) 0.01 — Table B.3
LAoccupancyoccupied 0.01, high occupancy 0.1
LBfire_riskno fire risk 0, ordinary 0.1, high fire risk 0.5, explosion risk 1
LCconsequence_of_failureno consequence 0, standard 0.01, critical 0.1

Protection Level Determination

If R1 > RT (10-5), lightning protection is required. The minimum LPL is the level whose PB reduction factor (efficiency) brings R1 ≤ RT.

LPLEfficiencyRolling SphereMesh Size
I0.9820 m5 × 5 m
II0.9530 m10 × 10 m
III0.9045 m15 × 15 m
IV0.8060 m20 × 20 m

Worked Examples

The 25 examples below are the validation cases for this calculation. Each one was produced by the calculation engine from the inputs shown, every figure was checked against the independent reference quoted at the end of the example, and the same cases are run against every engine build (see validation scorecard, tool fe_calc_lightning_risk; worked examples for every calculation).

#CaseAD (m²)ND (/yr)R1 (/yr)LPSR1 with LPSResult
1Small building among taller ones1,406.93.52 × 10−41.06 × 10−5class IV7.74 × 10−6FAIL
240 × 20 × 10 m building, all defaults7,227.47.23 × 10−32.17 × 10−4class I1.46 × 10−4FAIL
3Hilltop warehouse with high fire risk34,309.70.3430.024class I7.21 × 10−3FAIL
4Bonded building needing class IV3,087.93.09 × 10−33.18 × 10−5class IV7.10 × 10−6FAIL
5Bonded building needing class III7,227.47.23 × 10−37.44 × 10−5class III9.40 × 10−6FAIL
6Bonded building needing class II7,227.40.01081.12 × 10−4class II8.67 × 10−6FAIL
7Bonded building needing class I7,227.40.02172.21 × 10−4class I8.67 × 10−6FAIL
8Existing class III LPS already adequate7,227.47.23 × 10−39.40 × 10−6none–PASS
9Existing class IV LPS needs upgrading7,227.40.01082.49 × 10−5class II8.67 × 10−6FAIL
10Isolated building (C_D 1)2,649.91.32 × 10−31.52 × 10−5class IV4.64 × 10−6FAIL
11Small hut isolated on a hilltop (C_D 2)458.59.17 × 10−41.83 × 10−7none–PASS
12Metal roof and metal frame12,351.50.01244.94 × 10−6none–PASS
13Non-metal roof on a metal frame12,351.50.01852.41 × 10−5class IV9.26 × 10−6FAIL
14Thatched-roof cottage1,833.93.67 × 10−31.14 × 10−4class II9.90 × 10−6FAIL
15High-occupancy hall11,331.58.50 × 10−31.72 × 10−4class I8.84 × 10−5FAIL
16Structure with no fire risk20,361.70.04072.44 × 10−5class I2.44 × 10−5FAIL
17Explosion-risk process building6,427.40.02252.29 × 10−4class I9.00 × 10−6FAIL
18Telecom equipment with critical consequence1,372.42.06 × 10−32.06 × 10−4class I2.06 × 10−4FAIL
19Same telecom building with LPL III–IV SPDs1,372.42.06 × 10−31.07 × 10−5class I1.05 × 10−5FAIL
20Same telecom building with SPD level 31,372.42.06 × 10−32.47 × 10−6none–PASS
21LV and telecom lines combined7,227.47.23 × 10−34.31 × 10−6none–PASS
22LV + telecom with no life consequence4,809.64.81 × 10−39.62 × 10−7none–PASS
23No connected service lines554.58.32 × 10−41.66 × 10−7none–PASS
24300 m tower on a hilltop2,617,090.010.50.21class I0.209FAIL
25Smallest structure at the lowest flash density41.32.06 × 10−66.19 × 10−8none–PASS

Example 1 — Small building among taller ones

A 10 × 10 × 5 m building surrounded by higher structures (C_D 0.25) at N_G 1: with its unprotected LV line (P_C 1) R1 lands just above R_T and a class IV LPS is enough.

Given: Structure 10 × 10 × 5 m (L × W × H), ground flash density NG = 1 flashes/km²/yr, located surrounded by higher objects; non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: none; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 10 × 10 + 2 × 15 × (10 + 10) + π × 15² = 100.0 + 600.0 + 706.9 = 1,406.9 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 1 × 1,406.9 × 0.25 × 10−6 = 3.517 × 10−4 /yr
ProbabilitiesPA = 1 (none); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)1 = 1 (LV power line, n = 1, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 3.517 × 10−4 × 1 × 0.01 = 3.517 × 10−6; RB = ND·PB·LB = 3.517 × 10−4 × 0.1 × 0.1 = 3.517 × 10−6; RC = ND·PC·LC = 3.517 × 10−4 × 1 × 0.01 = 3.517 × 10−6
R1 checkR1 = RA + RB + RC = 3.517 × 10−6 + 3.517 × 10−6 + 3.517 × 10−6 → 1.055 × 10−5 > RT = 10−5/yr (105.5 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 3.517 × 10−6): class IV: 3.517 × 10−6 + 3.517 × 10−6 × 0.2 + 3.517 × 10−6 = 7.738 × 10−6 ≤ RT → class IV; rolling sphere 60 m, mesh 20 × 20 m (IEC 62305-3 Table 2)
Residual R1R1 with class IV LPS → 7.738 × 10−6 ≤ RT = 10−5/yr (77.4 %) PASS
Result1/2 checks pass → FAIL; R1 = 1.055 × 10−5/yr; recommended LPS: class IV; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 10 × 10 + 6 × 5 × (10 + 10) + 9π × 5² = 1406.9 m²; N_D = 1 × 1406.9 × 0.25 × 1e-6 = 0.0003517/yr; R_A = N_D × 1 × 0.01 = 3.517e-06, R_B = N_D × 0.1 × 0.1 = 3.517e-06, P_C = 1 − (1 − 1 × 1)^1 = 1 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0.01 = 3.517e-06; R1 = 1.055e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): IV, residual R1 = 7.738e-06; rolling sphere 60 m, mesh 20 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-10x10x5m-ng1-surrounded)

Example 2 — 40 × 20 × 10 m building, all defaults

With every factor at its default the touch/step component R_A alone exceeds R_T, so even a class I LPS leaves R1 above the limit.

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: none; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 7,227.4 × 0.5 × 10−6 = 7.227 × 10−3 /yr
ProbabilitiesPA = 1 (none); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)1 = 1 (LV power line, n = 1, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 7.227 × 10−3 × 1 × 0.01 = 7.227 × 10−5; RB = ND·PB·LB = 7.227 × 10−3 × 0.1 × 0.1 = 7.227 × 10−5; RC = ND·PC·LC = 7.227 × 10−3 × 1 × 0.01 = 7.227 × 10−5
R1 checkR1 = RA + RB + RC = 7.227 × 10−5 + 7.227 × 10−5 + 7.227 × 10−5 → 2.168 × 10−4 > RT = 10−5/yr (2,168.2 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 7.227 × 10−5): class IV: 7.227 × 10−5 + 7.227 × 10−5 × 0.2 + 7.227 × 10−5 = 1.590 × 10−4 > RT; class III: 7.227 × 10−5 + 7.227 × 10−5 × 0.1 + 7.227 × 10−5 = 1.518 × 10−4 > RT; class II: 7.227 × 10−5 + 7.227 × 10−5 × 0.05 + 7.227 × 10−5 = 1.482 × 10−4 > RT; class I: 7.227 × 10−5 + 7.227 × 10−5 × 0.02 + 7.227 × 10−5 = 1.460 × 10−4 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 1.460 × 10−4 > RT = 10−5/yr (1,459.9 %) FAIL
Result0/2 checks pass → FAIL; R1 = 2.168 × 10−4/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 0.000146 > 1e-05; the remaining risk is dominated by RA, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 2 × 7227.4 × 0.5 × 1e-6 = 0.007227/yr; R_A = N_D × 1 × 0.01 = 7.227e-05, R_B = N_D × 0.1 × 0.1 = 7.227e-05, P_C = 1 − (1 − 1 × 1)^1 = 1 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0.01 = 7.227e-05; R1 = 0.0002168 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 0.000146; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-40x20x10m-ng2-flat)

Example 3 — Hilltop warehouse with high fire risk

A large exposed warehouse (C_D 2, L_B 0.5) is far above R_T; class I is recommended but R_A keeps the residual risk above the limit.

Given: Structure 100 × 50 × 20 m (L × W × H), ground flash density NG = 5 flashes/km²/yr, located isolated on a hilltop or knoll (exposed); non-metallic roof and structure, high fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: none; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 100 × 50 + 2 × 60 × (100 + 50) + π × 60² = 5,000.0 + 18,000.0 + 11,309.7 = 34,309.7 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 5 × 34,309.7 × 2 × 10−6 = 0.3431 /yr
ProbabilitiesPA = 1 (none); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)1 = 1 (LV power line, n = 1, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.5 (high fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.3431 × 1 × 0.01 = 3.431 × 10−3; RB = ND·PB·LB = 0.3431 × 0.1 × 0.5 = 0.01715; RC = ND·PC·LC = 0.3431 × 1 × 0.01 = 3.431 × 10−3
R1 checkR1 = RA + RB + RC = 3.431 × 10−3 + 0.01715 + 3.431 × 10−3 → 0.02402 > RT = 10−5/yr (240,168.1 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 0.01715): class IV: 3.431 × 10−3 + 0.01715 × 0.2 + 3.431 × 10−3 = 0.01029 > RT; class III: 3.431 × 10−3 + 0.01715 × 0.1 + 3.431 × 10−3 = 8.577 × 10−3 > RT; class II: 3.431 × 10−3 + 0.01715 × 0.05 + 3.431 × 10−3 = 7.720 × 10−3 > RT; class I: 3.431 × 10−3 + 0.01715 × 0.02 + 3.431 × 10−3 = 7.205 × 10−3 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 7.205 × 10−3 > RT = 10−5/yr (72,050.4 %) FAIL
Result0/2 checks pass → FAIL; R1 = 0.02402/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 0.00721 > 1e-05; the remaining risk is dominated by RA, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 100 × 50 + 6 × 20 × (100 + 50) + 9π × 20² = 34309.7 m²; N_D = 5 × 34309.7 × 2 × 1e-6 = 0.3431/yr; R_A = N_D × 1 × 0.01 = 0.003431, R_B = N_D × 0.1 × 0.5 = 0.01715, P_C = 1 − (1 − 1 × 1)^1 = 1 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0.01 = 0.003431; R1 = 0.02402 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 0.007205; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-100x50x20m-ng5-exposed-high-fire)

Example 4 — Bonded building needing class IV

With equipotential bonding and coordinated SPDs only R_B matters, and a class IV LPS (P_B × 0.2) is the lowest class that meets R_T.

Given: Structure 30 × 15 × 6 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 30 × 15 + 2 × 18 × (30 + 15) + π × 18² = 450.0 + 1,620.0 + 1,017.9 = 3,087.9 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 3,087.9 × 0.5 × 10−6 = 3.088 × 10−3 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 3.088 × 10−3 × 0.01 × 0.01 = 3.088 × 10−7; RB = ND·PB·LB = 3.088 × 10−3 × 0.1 × 0.1 = 3.088 × 10−5; RC = ND·PC·LC = 3.088 × 10−3 × 0.02 × 0.01 = 6.176 × 10−7
R1 checkR1 = RA + RB + RC = 3.088 × 10−7 + 3.088 × 10−5 + 6.176 × 10−7 → 3.181 × 10−5 > RT = 10−5/yr (318.1 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 3.088 × 10−5): class IV: 3.088 × 10−7 + 3.088 × 10−5 × 0.2 + 6.176 × 10−7 = 7.102 × 10−6 ≤ RT → class IV; rolling sphere 60 m, mesh 20 × 20 m (IEC 62305-3 Table 2)
Residual R1R1 with class IV LPS → 7.102 × 10−6 ≤ RT = 10−5/yr (71.0 %) PASS
Result1/2 checks pass → FAIL; R1 = 3.181 × 10−5/yr; recommended LPS: class IV; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 30 × 15 + 6 × 6 × (30 + 15) + 9π × 6² = 3087.9 m²; N_D = 2 × 3087.9 × 0.5 × 1e-6 = 0.003088/yr; R_A = N_D × 0.01 × 0.01 = 3.088e-07, R_B = N_D × 0.1 × 0.1 = 3.088e-05, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 6.176e-07; R1 = 3.181e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): IV, residual R1 = 7.102e-06; rolling sphere 60 m, mesh 20 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-lpl-iv-selected)

Example 5 — Bonded building needing class III

The same protection measures on a larger building: class IV is not enough and class III (P_B × 0.1) is selected.

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 7,227.4 × 0.5 × 10−6 = 7.227 × 10−3 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 7.227 × 10−3 × 0.01 × 0.01 = 7.227 × 10−7; RB = ND·PB·LB = 7.227 × 10−3 × 0.1 × 0.1 = 7.227 × 10−5; RC = ND·PC·LC = 7.227 × 10−3 × 0.02 × 0.01 = 1.445 × 10−6
R1 checkR1 = RA + RB + RC = 7.227 × 10−7 + 7.227 × 10−5 + 1.445 × 10−6 → 7.444 × 10−5 > RT = 10−5/yr (744.4 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 7.227 × 10−5): class IV: 7.227 × 10−7 + 7.227 × 10−5 × 0.2 + 1.445 × 10−6 = 1.662 × 10−5 > RT; class III: 7.227 × 10−7 + 7.227 × 10−5 × 0.1 + 1.445 × 10−6 = 9.396 × 10−6 ≤ RT → class III; rolling sphere 45 m, mesh 15 × 15 m (IEC 62305-3 Table 2)
Residual R1R1 with class III LPS → 9.396 × 10−6 ≤ RT = 10−5/yr (94.0 %) PASS
Result1/2 checks pass → FAIL; R1 = 7.444 × 10−5/yr; recommended LPS: class III; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 2 × 7227.4 × 0.5 × 1e-6 = 0.007227/yr; R_A = N_D × 0.01 × 0.01 = 7.227e-07, R_B = N_D × 0.1 × 0.1 = 7.227e-05, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 1.445e-06; R1 = 7.444e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): III, residual R1 = 9.396e-06; rolling sphere 45 m, mesh 15 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-lpl-iii-selected)

Example 6 — Bonded building needing class II

Higher flash density (N_G 3) pushes the recommendation to class II (P_B × 0.05, 30 m rolling sphere).

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 3 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 3 × 7,227.4 × 0.5 × 10−6 = 0.01084 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.01084 × 0.01 × 0.01 = 1.084 × 10−6; RB = ND·PB·LB = 0.01084 × 0.1 × 0.1 = 1.084 × 10−4; RC = ND·PC·LC = 0.01084 × 0.02 × 0.01 = 2.168 × 10−6
R1 checkR1 = RA + RB + RC = 1.084 × 10−6 + 1.084 × 10−4 + 2.168 × 10−6 → 1.117 × 10−4 > RT = 10−5/yr (1,116.6 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 1.084 × 10−4): class IV: 1.084 × 10−6 + 1.084 × 10−4 × 0.2 + 2.168 × 10−6 = 2.493 × 10−5 > RT; class III: 1.084 × 10−6 + 1.084 × 10−4 × 0.1 + 2.168 × 10−6 = 1.409 × 10−5 > RT; class II: 1.084 × 10−6 + 1.084 × 10−4 × 0.05 + 2.168 × 10−6 = 8.673 × 10−6 ≤ RT → class II; rolling sphere 30 m, mesh 10 × 10 m (IEC 62305-3 Table 2)
Residual R1R1 with class II LPS → 8.673 × 10−6 ≤ RT = 10−5/yr (86.7 %) PASS
Result1/2 checks pass → FAIL; R1 = 1.117 × 10−4/yr; recommended LPS: class II; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 3 × 7227.4 × 0.5 × 1e-6 = 0.01084/yr; R_A = N_D × 0.01 × 0.01 = 1.084e-06, R_B = N_D × 0.1 × 0.1 = 0.0001084, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 2.168e-06; R1 = 0.0001117 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): II, residual R1 = 8.673e-06; rolling sphere 30 m, mesh 10 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-lpl-ii-selected)

Example 7 — Bonded building needing class I

At N_G 6 only a class I LPS (P_B × 0.02, 20 m sphere, 5 m mesh) brings R1 within R_T.

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 6 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: electrical insulation; surge protection: coordinated SPDs for LPL I; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 6 × 7,227.4 × 0.5 × 10−6 = 0.02168 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.01 × 1)1 = 0.01 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL I, PSPD = 0.01, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.02168 × 0.01 × 0.01 = 2.168 × 10−6; RB = ND·PB·LB = 0.02168 × 0.1 × 0.1 = 2.168 × 10−4; RC = ND·PC·LC = 0.02168 × 0.01 × 0.01 = 2.168 × 10−6
R1 checkR1 = RA + RB + RC = 2.168 × 10−6 + 2.168 × 10−4 + 2.168 × 10−6 → 2.212 × 10−4 > RT = 10−5/yr (2,211.6 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 2.168 × 10−4): class IV: 2.168 × 10−6 + 2.168 × 10−4 × 0.2 + 2.168 × 10−6 = 4.770 × 10−5 > RT; class III: 2.168 × 10−6 + 2.168 × 10−4 × 0.1 + 2.168 × 10−6 = 2.602 × 10−5 > RT; class II: 2.168 × 10−6 + 2.168 × 10−4 × 0.05 + 2.168 × 10−6 = 1.518 × 10−5 > RT; class I: 2.168 × 10−6 + 2.168 × 10−4 × 0.02 + 2.168 × 10−6 = 8.673 × 10−6 ≤ RT → class I; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 8.673 × 10−6 ≤ RT = 10−5/yr (86.7 %) PASS
Result1/2 checks pass → FAIL; R1 = 2.212 × 10−4/yr; recommended LPS: class I; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 6 × 7227.4 × 0.5 × 1e-6 = 0.02168/yr; R_A = N_D × 0.01 × 0.01 = 2.168e-06, R_B = N_D × 0.1 × 0.1 = 0.0002168, P_C = 1 − (1 − 0.01 × 1)^1 = 0.01 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.01, Table B.3); R_C = N_D × 0.01 × 0.01 = 2.168e-06; R1 = 0.0002212 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I, residual R1 = 8.673e-06; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-lpl-i-selected)

Example 8 — Existing class III LPS already adequate

An installed class III LPS reduces P_B to 0.01 and the building passes as it stands; no further LPS is recommended.

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL II; existing LPS: class III.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 7,227.4 × 0.5 × 10−6 = 7.227 × 10−3 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.1 (non-metallic roof and structure) × 0.1 (existing class III LPS) = 0.01; PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 7.227 × 10−3 × 0.01 × 0.01 = 7.227 × 10−7; RB = ND·PB·LB = 7.227 × 10−3 × 0.01 × 0.1 = 7.227 × 10−6; RC = ND·PC·LC = 7.227 × 10−3 × 0.02 × 0.01 = 1.445 × 10−6
R1 checkR1 = RA + RB + RC = 7.227 × 10−7 + 7.227 × 10−6 + 1.445 × 10−6 → 9.396 × 10−6 ≤ RT = 10−5/yr (94.0 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 9.396 × 10−6/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 2 × 7227.4 × 0.5 × 1e-6 = 0.007227/yr; R_A = N_D × 0.01 × 0.01 = 7.227e-07, R_B = N_D × 0.01 × 0.1 = 7.227e-06, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 1.445e-06; R1 = 9.396e-06 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-existing-lps-iii-passes)

Example 9 — Existing class IV LPS needs upgrading

An installed class IV LPS leaves R1 above R_T, so the tool recommends the class that does meet it.

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 3 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL II; existing LPS: class IV.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 3 × 7,227.4 × 0.5 × 10−6 = 0.01084 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.1 (non-metallic roof and structure) × 0.2 (existing class IV LPS) = 0.02; PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.01084 × 0.01 × 0.01 = 1.084 × 10−6; RB = ND·PB·LB = 0.01084 × 0.02 × 0.1 = 2.168 × 10−5; RC = ND·PC·LC = 0.01084 × 0.02 × 0.01 = 2.168 × 10−6
R1 checkR1 = RA + RB + RC = 1.084 × 10−6 + 2.168 × 10−5 + 2.168 × 10−6 → 2.493 × 10−5 > RT = 10−5/yr (249.3 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 1.084 × 10−4): class IV: 1.084 × 10−6 + 1.084 × 10−4 × 0.2 + 2.168 × 10−6 = 2.493 × 10−5 > RT; class III: 1.084 × 10−6 + 1.084 × 10−4 × 0.1 + 2.168 × 10−6 = 1.409 × 10−5 > RT; class II: 1.084 × 10−6 + 1.084 × 10−4 × 0.05 + 2.168 × 10−6 = 8.673 × 10−6 ≤ RT → class II; rolling sphere 30 m, mesh 10 × 10 m (IEC 62305-3 Table 2)
Residual R1R1 with class II LPS → 8.673 × 10−6 ≤ RT = 10−5/yr (86.7 %) PASS
Result1/2 checks pass → FAIL; R1 = 2.493 × 10−5/yr; recommended LPS: class II; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 3 × 7227.4 × 0.5 × 1e-6 = 0.01084/yr; R_A = N_D × 0.01 × 0.01 = 1.084e-06, R_B = N_D × 0.02 × 0.1 = 2.168e-05, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 2.168e-06; R1 = 2.493e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): II, residual R1 = 8.673e-06; rolling sphere 30 m, mesh 10 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-existing-lps-iv-upgrade)

Example 10 — Isolated building (C_D 1)

An isolated structure with no neighbours (location 'moderate', C_D 1) doubles N_D compared with the 'flat' case.

Given: Structure 25 × 12 × 6 m (L × W × H), ground flash density NG = 0.5 flashes/km²/yr, located isolated, no other objects nearby (moderate); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: warning notices; surge protection: coordinated SPDs for LPL III–IV; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 25 × 12 + 2 × 18 × (25 + 12) + π × 18² = 300.0 + 1,332.0 + 1,017.9 = 2,649.9 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 0.5 × 2,649.9 × 1 × 10−6 = 1.325 × 10−3 /yr
ProbabilitiesPA = 0.1 (warning notices); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.05 × 1)1 = 0.05 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL III–IV, PSPD = 0.05, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 1.325 × 10−3 × 0.1 × 0.01 = 1.325 × 10−6; RB = ND·PB·LB = 1.325 × 10−3 × 0.1 × 0.1 = 1.325 × 10−5; RC = ND·PC·LC = 1.325 × 10−3 × 0.05 × 0.01 = 6.625 × 10−7
R1 checkR1 = RA + RB + RC = 1.325 × 10−6 + 1.325 × 10−5 + 6.625 × 10−7 → 1.524 × 10−5 > RT = 10−5/yr (152.4 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 1.325 × 10−5): class IV: 1.325 × 10−6 + 1.325 × 10−5 × 0.2 + 6.625 × 10−7 = 4.637 × 10−6 ≤ RT → class IV; rolling sphere 60 m, mesh 20 × 20 m (IEC 62305-3 Table 2)
Residual R1R1 with class IV LPS → 4.637 × 10−6 ≤ RT = 10−5/yr (46.4 %) PASS
Result1/2 checks pass → FAIL; R1 = 1.524 × 10−5/yr; recommended LPS: class IV; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 25 × 12 + 6 × 6 × (25 + 12) + 9π × 6² = 2649.9 m²; N_D = 0.5 × 2649.9 × 1 × 1e-6 = 0.001325/yr; R_A = N_D × 0.1 × 0.01 = 1.325e-06, R_B = N_D × 0.1 × 0.1 = 1.325e-05, P_C = 1 − (1 − 0.05 × 1)^1 = 0.05 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.05, Table B.3); R_C = N_D × 0.05 × 0.01 = 6.625e-07; R1 = 1.524e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): IV, residual R1 = 4.637e-06; rolling sphere 60 m, mesh 20 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-moderate-location)

Example 11 — Small hut isolated on a hilltop (C_D 2)

An isolated structure on a hilltop or knoll takes C_D 2 (Table A.1), four times the 'flat' (same-height neighbours) value of 0.5 used by default.

Given: Structure 6 × 4 × 3 m (L × W × H), ground flash density NG = 1 flashes/km²/yr, located isolated on a hilltop or knoll (exposed); metal roof on a metal structure, ordinary fire risk, occupied; internal systems: no connected lines (standard consequence); touch/step measures: electrical insulation; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 6 × 4 + 2 × 9 × (6 + 4) + π × 9² = 24.0 + 180.0 + 254.5 = 458.5 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 1 × 458.5 × 2 × 10−6 = 9.169 × 10−4 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.001 (metal roof on a metal structure); PC = 0 (no connected lines: CLD = 0, Table B.4)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 9.169 × 10−4 × 0.01 × 0.01 = 9.169 × 10−8; RB = ND·PB·LB = 9.169 × 10−4 × 0.001 × 0.1 = 9.169 × 10−8; RC = ND·PC·LC = 9.169 × 10−4 × 0 × 0.01 = 0
R1 checkR1 = RA + RB + RC = 9.169 × 10−8 + 9.169 × 10−8 + 0 → 1.834 × 10−7 ≤ RT = 10−5/yr (1.8 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 1.834 × 10−7/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 6 × 4 + 6 × 3 × (6 + 4) + 9π × 3² = 458.5 m²; N_D = 1 × 458.5 × 2 × 1e-6 = 0.0009169/yr; R_A = N_D × 0.01 × 0.01 = 9.169e-08, R_B = N_D × 0.001 × 0.1 = 9.169e-08, P_C = 0 (no connected line, C_LD = 0, Table B.4); R_C = N_D × 0 × 0.01 = 0; R1 = 1.834e-07 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-hilltop-hut)

Example 12 — Metal roof and metal frame

A metal-clad steel-frame building has P_B 0.001, so R_B is negligible and the building passes without an LPS.

Given: Structure 60 × 30 × 12 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); metal roof on a metal structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: electrical insulation; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 60 × 30 + 2 × 36 × (60 + 30) + π × 36² = 1,800.0 + 6,480.0 + 4,071.5 = 12,351.5 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 12,351.5 × 0.5 × 10−6 = 0.01235 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.01235 × 0.01 × 0.01 = 1.235 × 10−6; RB = ND·PB·LB = 0.01235 × 0.001 × 0.1 = 1.235 × 10−6; RC = ND·PC·LC = 0.01235 × 0.02 × 0.01 = 2.470 × 10−6
R1 checkR1 = RA + RB + RC = 1.235 × 10−6 + 1.235 × 10−6 + 2.470 × 10−6 → 4.941 × 10−6 ≤ RT = 10−5/yr (49.4 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 4.941 × 10−6/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 60 × 30 + 6 × 12 × (60 + 30) + 9π × 12² = 12351.5 m²; N_D = 2 × 12351.5 × 0.5 × 1e-6 = 0.01235/yr; R_A = N_D × 0.01 × 0.01 = 1.235e-06, R_B = N_D × 0.001 × 0.1 = 1.235e-06, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 2.47e-06; R1 = 4.941e-06 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-metal-structure)

Example 13 — Non-metal roof on a metal frame

P_B 0.01 for a non-metallic roof on a steel frame: R1 is above R_T and a class IV LPS is enough.

Given: Structure 60 × 30 × 12 m (L × W × H), ground flash density NG = 3 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof on a metal structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: electrical insulation; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 60 × 30 + 2 × 36 × (60 + 30) + π × 36² = 1,800.0 + 6,480.0 + 4,071.5 = 12,351.5 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 3 × 12,351.5 × 0.5 × 10−6 = 0.01853 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.01 (non-metallic roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.01853 × 0.01 × 0.01 = 1.853 × 10−6; RB = ND·PB·LB = 0.01853 × 0.01 × 0.1 = 1.853 × 10−5; RC = ND·PC·LC = 0.01853 × 0.02 × 0.01 = 3.705 × 10−6
R1 checkR1 = RA + RB + RC = 1.853 × 10−6 + 1.853 × 10−5 + 3.705 × 10−6 → 2.409 × 10−5 > RT = 10−5/yr (240.9 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 1.853 × 10−5): class IV: 1.853 × 10−6 + 1.853 × 10−5 × 0.2 + 3.705 × 10−6 = 9.264 × 10−6 ≤ RT → class IV; rolling sphere 60 m, mesh 20 × 20 m (IEC 62305-3 Table 2)
Residual R1R1 with class IV LPS → 9.264 × 10−6 ≤ RT = 10−5/yr (92.6 %) PASS
Result1/2 checks pass → FAIL; R1 = 2.409 × 10−5/yr; recommended LPS: class IV; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 60 × 30 + 6 × 12 × (60 + 30) + 9π × 12² = 12351.5 m²; N_D = 3 × 12351.5 × 0.5 × 1e-6 = 0.01853/yr; R_A = N_D × 0.01 × 0.01 = 1.853e-06, R_B = N_D × 0.01 × 0.1 = 1.853e-05, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 3.705e-06; R1 = 2.409e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): IV, residual R1 = 9.264e-06; rolling sphere 60 m, mesh 20 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-non-metal-roof-metal-frame)

Example 14 — Thatched-roof cottage

A thatched roof (P_B 0.3) makes R_B dominant even on a small house; the LPS class follows from R_B alone.

Given: Structure 12 × 8 × 6 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located isolated, no other objects nearby (moderate); thatched roof, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: warning notices; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 12 × 8 + 2 × 18 × (12 + 8) + π × 18² = 96.0 + 720.0 + 1,017.9 = 1,833.9 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 1,833.9 × 1 × 10−6 = 3.668 × 10−3 /yr
ProbabilitiesPA = 0.1 (warning notices); PB = 0.3 (thatched roof); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 3.668 × 10−3 × 0.1 × 0.01 = 3.668 × 10−6; RB = ND·PB·LB = 3.668 × 10−3 × 0.3 × 0.1 = 1.100 × 10−4; RC = ND·PC·LC = 3.668 × 10−3 × 0.02 × 0.01 = 7.336 × 10−7
R1 checkR1 = RA + RB + RC = 3.668 × 10−6 + 1.100 × 10−4 + 7.336 × 10−7 → 1.144 × 10−4 > RT = 10−5/yr (1,144.3 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 1.100 × 10−4): class IV: 3.668 × 10−6 + 1.100 × 10−4 × 0.2 + 7.336 × 10−7 = 2.641 × 10−5 > RT; class III: 3.668 × 10−6 + 1.100 × 10−4 × 0.1 + 7.336 × 10−7 = 1.540 × 10−5 > RT; class II: 3.668 × 10−6 + 1.100 × 10−4 × 0.05 + 7.336 × 10−7 = 9.903 × 10−6 ≤ RT → class II; rolling sphere 30 m, mesh 10 × 10 m (IEC 62305-3 Table 2)
Residual R1R1 with class II LPS → 9.903 × 10−6 ≤ RT = 10−5/yr (99.0 %) PASS
Result1/2 checks pass → FAIL; R1 = 1.144 × 10−4/yr; recommended LPS: class II; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 12 × 8 + 6 × 6 × (12 + 8) + 9π × 6² = 1833.9 m²; N_D = 2 × 1833.9 × 1 × 1e-6 = 0.003668/yr; R_A = N_D × 0.1 × 0.01 = 3.668e-06, R_B = N_D × 0.3 × 0.1 = 0.00011, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 7.336e-07; R1 = 0.0001144 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): II, residual R1 = 9.903e-06; rolling sphere 30 m, mesh 10 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-thatched-roof)

Example 15 — High-occupancy hall

High occupancy raises L_A to 0.1; warning notices (P_A 0.1) are not enough to keep R_A within R_T.

Given: Structure 50 × 30 × 12 m (L × W × H), ground flash density NG = 1.5 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, high occupancy; internal systems: LV power line (standard consequence); touch/step measures: warning notices; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 50 × 30 + 2 × 36 × (50 + 30) + π × 36² = 1,500.0 + 5,760.0 + 4,071.5 = 11,331.5 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 1.5 × 11,331.5 × 0.5 × 10−6 = 8.499 × 10−3 /yr
ProbabilitiesPA = 0.1 (warning notices); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)1 = 0.02 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.1 (high occupancy); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 8.499 × 10−3 × 0.1 × 0.1 = 8.499 × 10−5; RB = ND·PB·LB = 8.499 × 10−3 × 0.1 × 0.1 = 8.499 × 10−5; RC = ND·PC·LC = 8.499 × 10−3 × 0.02 × 0.01 = 1.700 × 10−6
R1 checkR1 = RA + RB + RC = 8.499 × 10−5 + 8.499 × 10−5 + 1.700 × 10−6 → 1.717 × 10−4 > RT = 10−5/yr (1,716.7 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 8.499 × 10−5): class IV: 8.499 × 10−5 + 8.499 × 10−5 × 0.2 + 1.700 × 10−6 = 1.037 × 10−4 > RT; class III: 8.499 × 10−5 + 8.499 × 10−5 × 0.1 + 1.700 × 10−6 = 9.518 × 10−5 > RT; class II: 8.499 × 10−5 + 8.499 × 10−5 × 0.05 + 1.700 × 10−6 = 9.094 × 10−5 > RT; class I: 8.499 × 10−5 + 8.499 × 10−5 × 0.02 + 1.700 × 10−6 = 8.839 × 10−5 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 8.839 × 10−5 > RT = 10−5/yr (883.9 %) FAIL
Result0/2 checks pass → FAIL; R1 = 1.717 × 10−4/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 8.84e-05 > 1e-05; the remaining risk is dominated by RA, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 50 × 30 + 6 × 12 × (50 + 30) + 9π × 12² = 11331.5 m²; N_D = 1.5 × 11331.5 × 0.5 × 1e-6 = 0.008499/yr; R_A = N_D × 0.1 × 0.1 = 8.499e-05, R_B = N_D × 0.1 × 0.1 = 8.499e-05, P_C = 1 − (1 − 0.02 × 1)^1 = 0.02 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.02 × 0.01 = 1.7e-06; R1 = 0.0001717 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 8.839e-05; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-high-occupancy)

Example 16 — Structure with no fire risk

L_B 0 removes R_B entirely, so R1 = R_A + R_C stays above R_T and the recommended class I LPS cannot change it.

Given: Structure 80 × 40 × 15 m (L × W × H), ground flash density NG = 4 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, no fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: electrical insulation; surge protection: coordinated SPDs for LPL III–IV; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 80 × 40 + 2 × 45 × (80 + 40) + π × 45² = 3,200.0 + 10,800.0 + 6,361.7 = 20,361.7 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 4 × 20,361.7 × 0.5 × 10−6 = 0.04072 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.05 × 1)1 = 0.05 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL III–IV, PSPD = 0.05, Table B.3)
LossesLA = 0.01 (occupied); LB = 0 (no fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.04072 × 0.01 × 0.01 = 4.072 × 10−6; RB = ND·PB·LB = 0.04072 × 0.1 × 0 = 0; RC = ND·PC·LC = 0.04072 × 0.05 × 0.01 = 2.036 × 10−5
R1 checkR1 = RA + RB + RC = 4.072 × 10−6 + 0 + 2.036 × 10−5 → 2.443 × 10−5 > RT = 10−5/yr (244.3 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 0): class IV: 4.072 × 10−6 + 0 × 0.2 + 2.036 × 10−5 = 2.443 × 10−5 > RT; class III: 4.072 × 10−6 + 0 × 0.1 + 2.036 × 10−5 = 2.443 × 10−5 > RT; class II: 4.072 × 10−6 + 0 × 0.05 + 2.036 × 10−5 = 2.443 × 10−5 > RT; class I: 4.072 × 10−6 + 0 × 0.02 + 2.036 × 10−5 = 2.443 × 10−5 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 2.443 × 10−5 > RT = 10−5/yr (244.3 %) FAIL
Result0/2 checks pass → FAIL; R1 = 2.443 × 10−5/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 2.44e-05 > 1e-05; the remaining risk is dominated by RC, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 80 × 40 + 6 × 15 × (80 + 40) + 9π × 15² = 20361.7 m²; N_D = 4 × 20361.7 × 0.5 × 1e-6 = 0.04072/yr; R_A = N_D × 0.01 × 0.01 = 4.072e-06, R_B = N_D × 0.1 × 0 = 0, P_C = 1 − (1 − 0.05 × 1)^1 = 0.05 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.05, Table B.3); R_C = N_D × 0.05 × 0.01 = 2.036e-05; R1 = 2.443e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 2.443e-05; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-no-fire-risk)

Example 17 — Explosion-risk process building

L_B 1 for explosion risk on a steel-framed building (P_B 0.01): class II leaves R1 above R_T and class I is required.

Given: Structure 30 × 20 × 10 m (L × W × H), ground flash density NG = 7 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof on a metal structure, explosion risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL I; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 30 × 20 + 2 × 30 × (30 + 20) + π × 30² = 600.0 + 3,000.0 + 2,827.4 = 6,427.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 7 × 6,427.4 × 0.5 × 10−6 = 0.0225 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.01 (non-metallic roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.01 × 1)1 = 0.01 (LV power line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL I, PSPD = 0.01, Table B.3)
LossesLA = 0.01 (occupied); LB = 1 (explosion risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 0.0225 × 0.01 × 0.01 = 2.250 × 10−6; RB = ND·PB·LB = 0.0225 × 0.01 × 1 = 2.250 × 10−4; RC = ND·PC·LC = 0.0225 × 0.01 × 0.01 = 2.250 × 10−6
R1 checkR1 = RA + RB + RC = 2.250 × 10−6 + 2.250 × 10−4 + 2.250 × 10−6 → 2.295 × 10−4 > RT = 10−5/yr (2,294.6 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 2.250 × 10−4): class IV: 2.250 × 10−6 + 2.250 × 10−4 × 0.2 + 2.250 × 10−6 = 4.949 × 10−5 > RT; class III: 2.250 × 10−6 + 2.250 × 10−4 × 0.1 + 2.250 × 10−6 = 2.700 × 10−5 > RT; class II: 2.250 × 10−6 + 2.250 × 10−4 × 0.05 + 2.250 × 10−6 = 1.575 × 10−5 > RT; class I: 2.250 × 10−6 + 2.250 × 10−4 × 0.02 + 2.250 × 10−6 = 8.998 × 10−6 ≤ RT → class I; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 8.998 × 10−6 ≤ RT = 10−5/yr (90.0 %) PASS
Result1/2 checks pass → FAIL; R1 = 2.295 × 10−4/yr; recommended LPS: class I; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 30 × 20 + 6 × 10 × (30 + 20) + 9π × 10² = 6427.4 m²; N_D = 7 × 6427.4 × 0.5 × 1e-6 = 0.0225/yr; R_A = N_D × 0.01 × 0.01 = 2.25e-06, R_B = N_D × 0.01 × 1 = 0.000225, P_C = 1 − (1 − 0.01 × 1)^1 = 0.01 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.01, Table B.3); R_C = N_D × 0.01 × 0.01 = 2.25e-06; R1 = 0.0002295 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I, residual R1 = 8.998e-06; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-explosion-risk)

Example 18 — Telecom equipment with critical consequence

One unshielded telecom line with no SPDs (P_C 1) and a critical failure consequence (L_C 0.1): R_C dominates and an LPS cannot fix it.

Given: Structure 20 × 10 × 4 m (L × W × H), ground flash density NG = 6 flashes/km²/yr, located surrounded by higher objects; metal roof on a metal structure, ordinary fire risk, occupied; internal systems: telecom line (critical consequence); touch/step measures: electrical insulation; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 20 × 10 + 2 × 12 × (20 + 10) + π × 12² = 200.0 + 720.0 + 452.4 = 1,372.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 6 × 1,372.4 × 0.25 × 10−6 = 2.059 × 10−3 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)1 = 1 (telecom line, n = 1, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.1 (critical consequence)
Risk componentsRA = ND·PA·LA = 2.059 × 10−3 × 0.01 × 0.01 = 2.059 × 10−7; RB = ND·PB·LB = 2.059 × 10−3 × 0.001 × 0.1 = 2.059 × 10−7; RC = ND·PC·LC = 2.059 × 10−3 × 1 × 0.1 = 2.059 × 10−4
R1 checkR1 = RA + RB + RC = 2.059 × 10−7 + 2.059 × 10−7 + 2.059 × 10−4 → 2.063 × 10−4 > RT = 10−5/yr (2,062.7 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 2.059 × 10−7): class IV: 2.059 × 10−7 + 2.059 × 10−7 × 0.2 + 2.059 × 10−4 = 2.061 × 10−4 > RT; class III: 2.059 × 10−7 + 2.059 × 10−7 × 0.1 + 2.059 × 10−4 = 2.061 × 10−4 > RT; class II: 2.059 × 10−7 + 2.059 × 10−7 × 0.05 + 2.059 × 10−4 = 2.061 × 10−4 > RT; class I: 2.059 × 10−7 + 2.059 × 10−7 × 0.02 + 2.059 × 10−4 = 2.061 × 10−4 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 2.061 × 10−4 > RT = 10−5/yr (2,060.7 %) FAIL
Result0/2 checks pass → FAIL; R1 = 2.063 × 10−4/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 0.000206 > 1e-05; the remaining risk is dominated by RC, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 20 × 10 + 6 × 4 × (20 + 10) + 9π × 4² = 1372.4 m²; N_D = 6 × 1372.4 × 0.25 × 1e-6 = 0.002059/yr; R_A = N_D × 0.01 × 0.01 = 2.059e-07, R_B = N_D × 0.001 × 0.1 = 2.059e-07, P_C = 1 − (1 − 1 × 1)^1 = 1 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0.1 = 0.0002059; R1 = 0.0002063 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 0.0002061; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-telecom-critical)

Example 19 — Same telecom building with LPL III–IV SPDs

SPDs designed for LPL III–IV (P_SPD 0.05, Table B.3) leave R_C = N_D × 0.05 × 0.1 just above R_T; an LPS cannot remove it, so better-coordinated SPDs are needed.

Given: Structure 20 × 10 × 4 m (L × W × H), ground flash density NG = 6 flashes/km²/yr, located surrounded by higher objects; metal roof on a metal structure, ordinary fire risk, occupied; internal systems: telecom line (critical consequence); touch/step measures: electrical insulation; surge protection: coordinated SPDs for LPL III–IV; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 20 × 10 + 2 × 12 × (20 + 10) + π × 12² = 200.0 + 720.0 + 452.4 = 1,372.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 6 × 1,372.4 × 0.25 × 10−6 = 2.059 × 10−3 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.05 × 1)1 = 0.05 (telecom line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL III–IV, PSPD = 0.05, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.1 (critical consequence)
Risk componentsRA = ND·PA·LA = 2.059 × 10−3 × 0.01 × 0.01 = 2.059 × 10−7; RB = ND·PB·LB = 2.059 × 10−3 × 0.001 × 0.1 = 2.059 × 10−7; RC = ND·PC·LC = 2.059 × 10−3 × 0.05 × 0.1 = 1.029 × 10−5
R1 checkR1 = RA + RB + RC = 2.059 × 10−7 + 2.059 × 10−7 + 1.029 × 10−5 → 1.070 × 10−5 > RT = 10−5/yr (107.0 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 2.059 × 10−7): class IV: 2.059 × 10−7 + 2.059 × 10−7 × 0.2 + 1.029 × 10−5 = 1.054 × 10−5 > RT; class III: 2.059 × 10−7 + 2.059 × 10−7 × 0.1 + 1.029 × 10−5 = 1.052 × 10−5 > RT; class II: 2.059 × 10−7 + 2.059 × 10−7 × 0.05 + 1.029 × 10−5 = 1.051 × 10−5 > RT; class I: 2.059 × 10−7 + 2.059 × 10−7 × 0.02 + 1.029 × 10−5 = 1.050 × 10−5 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 1.050 × 10−5 > RT = 10−5/yr (105.0 %) FAIL
Result0/2 checks pass → FAIL; R1 = 1.070 × 10−5/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 1.05e-05 > 1e-05; the remaining risk is dominated by RC, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 20 × 10 + 6 × 4 × (20 + 10) + 9π × 4² = 1372.4 m²; N_D = 6 × 1372.4 × 0.25 × 1e-6 = 0.002059/yr; R_A = N_D × 0.01 × 0.01 = 2.059e-07, R_B = N_D × 0.001 × 0.1 = 2.059e-07, P_C = 1 − (1 − 0.05 × 1)^1 = 0.05 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.05, Table B.3); R_C = N_D × 0.05 × 0.1 = 1.029e-05; R1 = 1.07e-05 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 1.05e-05; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-telecom-critical-spd1)

Example 20 — Same telecom building with SPD level 3

Coordinated SPDs designed for LPL I (P_SPD 0.01, Table B.3) cut P_C to 0.01 and the building passes.

Given: Structure 20 × 10 × 4 m (L × W × H), ground flash density NG = 6 flashes/km²/yr, located surrounded by higher objects; metal roof on a metal structure, ordinary fire risk, occupied; internal systems: telecom line (critical consequence); touch/step measures: electrical insulation; surge protection: coordinated SPDs for LPL I; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 20 × 10 + 2 × 12 × (20 + 10) + π × 12² = 200.0 + 720.0 + 452.4 = 1,372.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 6 × 1,372.4 × 0.25 × 10−6 = 2.059 × 10−3 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.01 × 1)1 = 0.01 (telecom line, n = 1, unshielded CLD = 1; coordinated SPDs for LPL I, PSPD = 0.01, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.1 (critical consequence)
Risk componentsRA = ND·PA·LA = 2.059 × 10−3 × 0.01 × 0.01 = 2.059 × 10−7; RB = ND·PB·LB = 2.059 × 10−3 × 0.001 × 0.1 = 2.059 × 10−7; RC = ND·PC·LC = 2.059 × 10−3 × 0.01 × 0.1 = 2.059 × 10−6
R1 checkR1 = RA + RB + RC = 2.059 × 10−7 + 2.059 × 10−7 + 2.059 × 10−6 → 2.470 × 10−6 ≤ RT = 10−5/yr (24.7 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 2.470 × 10−6/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 20 × 10 + 6 × 4 × (20 + 10) + 9π × 4² = 1372.4 m²; N_D = 6 × 1372.4 × 0.25 × 1e-6 = 0.002059/yr; R_A = N_D × 0.01 × 0.01 = 2.059e-07, R_B = N_D × 0.001 × 0.1 = 2.059e-07, P_C = 1 − (1 − 0.01 × 1)^1 = 0.01 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.01, Table B.3); R_C = N_D × 0.01 × 0.1 = 2.059e-06; R1 = 2.47e-06 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-telecom-critical-spd3)

Example 21 — LV and telecom lines combined

Two connected lines with LPL II SPDs: P_C = 1 − (1 − 0.02)² = 0.0396, almost twice the single-line 0.02 — adding a line raises the internal-systems risk; R1 still meets R_T.

Given: Structure 40 × 20 × 10 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); metal roof on a metal structure, ordinary fire risk, occupied; internal systems: LV power and telecom lines (standard consequence); touch/step measures: equipotential bonding; surge protection: coordinated SPDs for LPL II; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 40 × 20 + 2 × 30 × (40 + 20) + π × 30² = 800.0 + 3,600.0 + 2,827.4 = 7,227.4 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 7,227.4 × 0.5 × 10−6 = 7.227 × 10−3 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 0.02 × 1)2 = 0.0396 (LV power and telecom lines, n = 2, unshielded CLD = 1; coordinated SPDs for LPL II, PSPD = 0.02, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 7.227 × 10−3 × 0.01 × 0.01 = 7.227 × 10−7; RB = ND·PB·LB = 7.227 × 10−3 × 0.001 × 0.1 = 7.227 × 10−7; RC = ND·PC·LC = 7.227 × 10−3 × 0.0396 × 0.01 = 2.862 × 10−6
R1 checkR1 = RA + RB + RC = 7.227 × 10−7 + 7.227 × 10−7 + 2.862 × 10−6 → 4.308 × 10−6 ≤ RT = 10−5/yr (43.1 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 4.308 × 10−6/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 40 × 20 + 6 × 10 × (40 + 20) + 9π × 10² = 7227.4 m²; N_D = 2 × 7227.4 × 0.5 × 1e-6 = 0.007227/yr; R_A = N_D × 0.01 × 0.01 = 7.227e-07, R_B = N_D × 0.001 × 0.1 = 7.227e-07, P_C = 1 − (1 − 0.02 × 1)^2 = 0.0396 (2 unshielded line(s), C_LD = 1, Table B.4; P_SPD 0.02, Table B.3); R_C = N_D × 0.0396 × 0.01 = 2.862e-06; R1 = 4.308e-06 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-lv-and-telecom-spd2-combined)

Example 22 — LV + telecom with no life consequence

LV and telecom lines without SPDs give P_C = 1, but no consequence of failure (L_C 0) makes R_C = 0.

Given: Structure 30 × 20 × 8 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located among objects of the same height or smaller (flat); metal roof on a metal structure, ordinary fire risk, occupied; internal systems: LV power and telecom lines (no consequence for life); touch/step measures: equipotential bonding; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 30 × 20 + 2 × 24 × (30 + 20) + π × 24² = 600.0 + 2,400.0 + 1,809.6 = 4,809.6 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 4,809.6 × 0.5 × 10−6 = 4.810 × 10−3 /yr
ProbabilitiesPA = 0.01 (equipotential bonding); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)2 = 1 (LV power and telecom lines, n = 2, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0 (no consequence for life)
Risk componentsRA = ND·PA·LA = 4.810 × 10−3 × 0.01 × 0.01 = 4.810 × 10−7; RB = ND·PB·LB = 4.810 × 10−3 × 0.001 × 0.1 = 4.810 × 10−7; RC = ND·PC·LC = 4.810 × 10−3 × 1 × 0 = 0
R1 checkR1 = RA + RB + RC = 4.810 × 10−7 + 4.810 × 10−7 + 0 → 9.619 × 10−7 ≤ RT = 10−5/yr (9.6 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 9.619 × 10−7/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 30 × 20 + 6 × 8 × (30 + 20) + 9π × 8² = 4809.6 m²; N_D = 2 × 4809.6 × 0.5 × 1e-6 = 0.00481/yr; R_A = N_D × 0.01 × 0.01 = 4.81e-07, R_B = N_D × 0.001 × 0.1 = 4.81e-07, P_C = 1 − (1 − 1 × 1)^2 = 1 (2 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0 = 0; R1 = 9.619e-07 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-lv-and-telecom-no-consequence)

Example 23 — No connected service lines

A stand-alone shed with no incoming lines has C_LD 0 (Table B.4), so P_C = 0 and R_C = 0 even without SPDs.

Given: Structure 8 × 6 × 3 m (L × W × H), ground flash density NG = 3 flashes/km²/yr, located among objects of the same height or smaller (flat); metal roof on a metal structure, ordinary fire risk, occupied; internal systems: no connected lines (standard consequence); touch/step measures: electrical insulation; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 8 × 6 + 2 × 9 × (8 + 6) + π × 9² = 48.0 + 252.0 + 254.5 = 554.5 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 3 × 554.5 × 0.5 × 10−6 = 8.317 × 10−4 /yr
ProbabilitiesPA = 0.01 (electrical insulation); PB = 0.001 (metal roof on a metal structure); PC = 0 (no connected lines: CLD = 0, Table B.4)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 8.317 × 10−4 × 0.01 × 0.01 = 8.317 × 10−8; RB = ND·PB·LB = 8.317 × 10−4 × 0.001 × 0.1 = 8.317 × 10−8; RC = ND·PC·LC = 8.317 × 10−4 × 0 × 0.01 = 0
R1 checkR1 = RA + RB + RC = 8.317 × 10−8 + 8.317 × 10−8 + 0 → 1.663 × 10−7 ≤ RT = 10−5/yr (1.7 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 1.663 × 10−7/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 8 × 6 + 6 × 3 × (8 + 6) + 9π × 3² = 554.5 m²; N_D = 3 × 554.5 × 0.5 × 1e-6 = 0.0008317/yr; R_A = N_D × 0.01 × 0.01 = 8.317e-08, R_B = N_D × 0.001 × 0.1 = 8.317e-08, P_C = 0 (no connected line, C_LD = 0, Table B.4); R_C = N_D × 0 × 0.01 = 0; R1 = 1.663e-07 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-no-internal-systems)

Example 24 — 300 m tower on a hilltop

At the 300 m height limit the 3H collection radius dominates (A_D ≈ 2.6 km²): dozens of flashes a year, so class I is recommended and R_A and R_C still exceed R_T.

Given: Structure 20 × 20 × 300 m (L × W × H), ground flash density NG = 2 flashes/km²/yr, located isolated on a hilltop or knoll (exposed); metal roof on a metal structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: none; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 20 × 20 + 2 × 900 × (20 + 20) + π × 900² = 400.0 + 72,000.0 + 2,544,690.0 = 2,617,090.0 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 2 × 2,617,090.0 × 2 × 10−6 = 10.47 /yr
ProbabilitiesPA = 1 (none); PB = 0.001 (metal roof on a metal structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)1 = 1 (LV power line, n = 1, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 10.47 × 1 × 0.01 = 0.1047; RB = ND·PB·LB = 10.47 × 0.001 × 0.1 = 1.047 × 10−3; RC = ND·PC·LC = 10.47 × 1 × 0.01 = 0.1047
R1 checkR1 = RA + RB + RC = 0.1047 + 1.047 × 10−3 + 0.1047 → 0.2104 > RT = 10−5/yr (2,104,140.4 %) FAIL
LPS selectionTry classes from IV, PB × 0.2 / 0.1 / 0.05 / 0.02, R1 = RA + ND·PB·LB × factor + RC (unprotected ND·PB·LB = 1.047 × 10−3): class IV: 0.1047 + 1.047 × 10−3 × 0.2 + 0.1047 = 0.2096 > RT; class III: 0.1047 + 1.047 × 10−3 × 0.1 + 0.1047 = 0.2095 > RT; class II: 0.1047 + 1.047 × 10−3 × 0.05 + 0.1047 = 0.2094 > RT; class I: 0.1047 + 1.047 × 10−3 × 0.02 + 0.1047 = 0.2094 > RT — no class achieves RT, class I recommended as the ceiling; rolling sphere 20 m, mesh 5 × 5 m (IEC 62305-3 Table 2)
Residual R1R1 with class I LPS → 0.2094 > RT = 10−5/yr (2,093,881.4 %) FAIL
Result0/2 checks pass → FAIL; R1 = 0.2104/yr; recommended LPS: class I; governing: risk r1 with recommended lps. Even an LPS of class I leaves R1 = 0.209 > 1e-05; the remaining risk is dominated by RA, which an LPS does not reduce in this engine — add touch/step protection measures (RA) or coordinated SPDs (RC).
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 20 × 20 + 6 × 300 × (20 + 20) + 9π × 300² = 2617090.0 m²; N_D = 2 × 2617090.0 × 2 × 1e-6 = 10.47/yr; R_A = N_D × 1 × 0.01 = 0.1047, R_B = N_D × 0.001 × 0.1 = 0.001047, P_C = 1 − (1 − 1 × 1)^1 = 1 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0.01 = 0.1047; R1 = 0.2104 > R_T 1e-5 (Table 4); lowest LPS class with R1 ≤ R_T (P_B × 0.2/0.1/0.05/0.02 for IV/III/II/I, Table B.2): I (none suffices, I is the ceiling), residual R1 = 0.2094; rolling sphere 20 m, mesh 5 m (IEC 62305-3 Table 2). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-tall-tower-300m)

Example 25 — Smallest structure at the lowest flash density

A 1 × 1 × 1 m kiosk at N_G 0.1 (both at their input minimums) has a negligible risk.

Given: Structure 1 × 1 × 1 m (L × W × H), ground flash density NG = 0.1 flashes/km²/yr, located among objects of the same height or smaller (flat); non-metallic roof and structure, ordinary fire risk, occupied; internal systems: LV power line (standard consequence); touch/step measures: none; surge protection: no coordinated SPDs; existing LPS: none.

Collection areaAD = L·W + 2·(3H)·(L + W) + π·(3H)² = 1 × 1 + 2 × 3 × (1 + 1) + π × 3² = 1.0 + 12.0 + 28.3 = 41.3 m²
Dangerous eventsND = NG × AD × CD × 10−6 = 0.1 × 41.3 × 0.5 × 10−6 = 2.064 × 10−6 /yr
ProbabilitiesPA = 1 (none); PB = 0.1 (non-metallic roof and structure); PC = 1 − (1 − PSPD·CLD)n = 1 − (1 − 1 × 1)1 = 1 (LV power line, n = 1, unshielded CLD = 1; no coordinated SPDs, PSPD = 1, Table B.3)
LossesLA = 0.01 (occupied); LB = 0.1 (ordinary fire risk); LC = 0.01 (standard consequence)
Risk componentsRA = ND·PA·LA = 2.064 × 10−6 × 1 × 0.01 = 2.064 × 10−8; RB = ND·PB·LB = 2.064 × 10−6 × 0.1 × 0.1 = 2.064 × 10−8; RC = ND·PC·LC = 2.064 × 10−6 × 1 × 0.01 = 2.064 × 10−8
R1 checkR1 = RA + RB + RC = 2.064 × 10−8 + 2.064 × 10−8 + 2.064 × 10−8 → 6.191 × 10−8 ≤ RT = 10−5/yr (0.6 %) PASS
LPS selectionR1 ≤ RT: no (further) lightning protection system is required
Result1/1 checks pass → PASS; R1 = 6.191 × 10−8/yr; recommended LPS: none; governing: risk r1
ReferenceHand calculation, IEC 62305-2:2010 Annex A: A_D = 1 × 1 + 6 × 1 × (1 + 1) + 9π × 1² = 41.3 m²; N_D = 0.1 × 41.3 × 0.5 × 1e-6 = 2.064e-06/yr; R_A = N_D × 1 × 0.01 = 2.064e-08, R_B = N_D × 0.1 × 0.1 = 2.064e-08, P_C = 1 − (1 − 1 × 1)^1 = 1 (1 unshielded line(s), C_LD = 1, Table B.4; P_SPD 1, Table B.3); R_C = N_D × 1 × 0.01 = 2.064e-08; R1 = 6.191e-08 ≤ R_T 1e-5 (Table 4). P_A, P_B and L factors are the tool's published category values (help page factor table); P_C per IEC 62305-2 B.4 with unshielded lines (C_LD 1, Table B.4) and P_SPD from Table B.3. (validation case c0038-minimum-inputs)

Standards & References

  • IEC 62305-1:2010 — Protection against lightning: General principles
  • IEC 62305-2:2010 — Protection against lightning: Risk management. Primary reference for risk assessment methodology.
  • IEC 62305-3:2010 — Protection against lightning: Physical damage and life hazard
  • IEC 62305-4:2010 — Protection against lightning: Electrical and electronic systems
  • AS/NZS 1768:2007 — Lightning protection (Australian/NZ implementation)

Tips & Limitations

  • This calculator implements Risk R1 (loss of human life) only. R4 (economic loss) uses the same framework but with different tolerable risk (10-3).
  • Ground flash density Ng should come from local meteorological data. In Australia, typical values range from 0.5 (Tasmania) to 12 (Darwin).
  • The location factor Cd significantly affects results. Use “moderate” (Cd = 1) for an isolated structure with no other objects nearby and “exposed” (Cd = 2) only for an isolated structure on a hilltop or knoll (IEC 62305-2 Table A.1).
  • An LPS reduces only RB. When RA (touch/step) or RC (internal systems) alone exceeds 10-5, even LPL I cannot achieve the tolerable risk: the calculator still reports LPL I and the residual risk check fails — add touch/step measures or coordinated SPDs.
  • Existing LPS reduces risk through the PB efficiency factor. If an existing LPS is already installed but the assessment still shows FAIL, a higher-level LPS is needed.
  • Surge protection devices (SPDs) reduce the PC component (internal system failures) but do not affect the physical damage risk RB. Even SPDs designed for LPL I only reduce PC to 0.01 per line, so with a critical failure consequence RC can still govern.
  • For structures with explosion risk, R1 is almost always above the tolerable threshold — LPL I is typically required.

Developer Guide — Architecture

This calculator follows the standard calcs component pattern:

components/c0038_lightning_risk_assessment/
├── __init__.py              # Docstring
├── apps.py                  # Django AppConfig
├── calculations.py          # Pure Python — IEC 62305-2 tables and formulas
├── component.py             # Schema, Calculator class, builders, registration
├── equations.py             # LaTeX equation templates
├── excel_generator.py       # Excel report generator
└── templates/.../sidebar_form.html  # Vue 3 sidebar form

This is the most table-heavy calc — calculations.py contains all IEC 62305-2 lookup tables as Python dictionaries.

Developer Guide — Code Paths

PurposeFileKey Function / Class
Collection areacalculations.pycalculate_collection_area(L, W, H)
Expected strikescalculations.pycalculate_expected_strikes(Ng, Ad, Cd)
Internal systems PCcalculations.pycalculate_internal_systems_probability(n_lines, P_SPD, C_LD)
Risk componentscalculations.pycalculate_risk_components()
Protection levelcalculations.pydetermine_protection_level()
Main entrycalculations.pycalculate_lightning_risk(data)
Validationcomponent.pyLightningRiskCalculator.validate_parameters()
Excel reportexcel_generator.pycreate_c0038_excel_report(calculation)
Registrationcomponent.pyregister_component(registry)

Developer Guide — Testing

# Run all tests for this component
pytest calcs/test_c0038_lightning_risk_assessment.py -v

Test coverage includes:

  • TestCollectionArea — geometric area calculation
  • TestExpectedStrikes — Nd calculation with various Ng and Cd
  • TestRiskComponents — individual risk component calculations
  • TestNoProtectionNeeded — small/sheltered structures
  • TestProtectionRequired — large/exposed structures
  • TestProtectionLevel — correct LPL determination
  • TestExistingLPS — risk reduction from existing protection
  • TestInternalSystemsProbability — PC per IEC 62305-2 B.4 (PSPD Table B.3, lines combined)
  • TestLocationFactors — CD per IEC 62305-2 Table A.1
  • TestCalculateLightningRisk — end-to-end integration
  • TestCalculatorClass — validation, round-trip, registration